Juggins Road Improvements

Juggins Road Project Map

STATE ROUTE 711

DESCRIPTION

  • Extends from the intersection with Chadwick Drive (SR-766) to 0.4 miles north of the intersection with Chadwick Drive
  • Project length of 0.4 miles
  • Provide wider travel lanes 
  • Paved asphalt concrete surface 
  • Improvements to drainage with curb & gutter   
  • Dedicated right turn lane to serve the new Anne E. Moncure Elementary School  
  • Safer roadway for the traveling public & school buses

UPDATE  NOVEMBER 2018

  • Final plans have been re-submitted to VDOT 
  • Verizon has completed its utility relocations
  • Columbia Gas line relocation is complete
  • Preparing contract for advertisement by end of November
  • Will ensure completion by end of June 2019 for Schools to start moving in equipment 
  • Working with VDOT to include “Incentive” clause in contract 
  • Projected construction duration is four months